Substation Scout

Peregrine BESS 2

ERCOT queue ID 25INR0078 Terminal status

Queue ID25INR0078
Project namePeregrine BESS 2
Status (as published)Cancelled
SubstationRAPTOR7A
Point of interconnection8673 RAPTOR7A 345kV
CountyGoliad
StateTX
Voltage345 kV
Capacity150 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-07-01
Source datasetcancelled

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Terminal status 150 SS Completed, FIS Started, No IA → Cancelled

Full change log →

Additional filed fields

Fuel CodeBattery Storage
Size CategoryLarge

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.