Substation Scout

Sombrero Solar

ERCOT queue ID 25INR0057

Queue ID25INR0057
Project nameSombrero Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationTap Big Hill - Orsted
Point of interconnectionTap 345kV 76003 Big Hill - 60708 Orsted
CountySchleicher
StateTX
Voltage345 kV
Capacity351.9 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-05-31
Source datasetlarge

Additional filed fields

Interconnecting EntityAurora Solar LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete44738
Air PermitNot Required
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.