Exodus BESS

ERCOT queue ID 24INR0459 Terminal status

Queue ID24INR0459
Project nameExodus BESS
Status (as published)Cancelled
SubstationTap Austrop – Zorn
Point of interconnectionTap 345kV 7040 Austrop – 7042 Zorn
CountyCaldwell
StateTX
Voltage345 kV
Capacity201.4 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-12-01
Source datasetcancelled

Tracked changes

1 change observed between weekly snapshots of the ERCOT queue since ERCOT tracking began on August 27, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-05 Terminal status 201.4 SS Completed, FIS Started, No IA → Cancelled

Full change log →

Additional filed fields

Fuel CodeBattery Storage
Size CategoryLarge

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.