Substation Scout

Razorbill Storage

ERCOT queue ID 22INR0382

Queue ID22INR0382
Project nameRazorbill Storage
Status (as published)SS Completed, FIS Started, No IA
Substationtap STP to Hillje Ckt 64
Point of interconnectiontap 345kV 5915 STP to 44200 Hillje 345kV Ckt 64
CountyMatagorda
StateTX
Voltage345 kV
Capacity120 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2027-12-15
Source datasetlarge

Additional filed fields

Interconnecting EntityRWE Solar Development, LLC
Cdr ZoneCOASTAL
Fuel CodeOTH
Technology CodeBA
Screening Study Complete44132
Air PermitNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.