Substation Scout

Pearl Crescent Storage

ERCOT queue ID 21INR0470

Queue ID21INR0470
Project namePearl Crescent Storage
Status (as published)SS Completed, FIS Started, No IA
SubstationRock Island ()
Point of interconnectionRock Island (57640) 138kV
CountyColorado
StateTX
Voltage138 kV
Capacity50.3 MW
Resource (as published)OTH/BA
Resource categoryBattery (normalised for filtering)
Target commercial operation2026-12-15
Source datasetlarge

Additional filed fields

Interconnecting EntityRWE Solar Development, LLC
Cdr ZoneSOUTH
Fuel CodeOTH
Technology CodeBA
Screening Study Complete43902