Substation Scout

Hart Wind (Old POI)

ERCOT queue ID 16INR0033 Terminal status

Queue ID16INR0033
Project nameHart Wind (Old POI)
Status (as published)Inactive
SubstationNot reported
Point of interconnectionNot reported
CountyCastro
StateTX
VoltageNot reported
Capacity165 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operationNot reported
Source datasetinactive

Additional filed fields

Fuel CodeWind
Size CategoryLarge