Queue IDProjectkVMWResourceStatus
26INR0120 Bramble Energy Center 138 225.1 Battery SS Completed, FIS Started, No IA
26INR0179 SunShiner ESS n/r 200 Battery SS Completed, FIS Started, No IA
27INR0274 Flying Kite Bess 138 104.9 Battery SS Completed, FIS Started, No IA
25INR0304 Flying Kite Solar 138 80.4 Solar SS Completed, FIS Started, IA
27INR0380 La Mancha Solar SLF 69 40.9 Solar SS Completed, FIS Started, No IA
27INR0381 La Mancha Storage SLF 69 40.9 Battery SS Completed, FIS Started, No IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.