Duke Energy request PP00051
Duke Energy queue ID PP00051
Queue request PP00051 was listed in the Duke Energy interconnection queue at the end of 2025 as a 80 MW project in Duplin County, NC, according to Berkeley Lab’s queue data file. The filing names Tri-County EMC Mt Olive POD 115 Tap Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of February 28, 2029.
| Queue ID | PP00051 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Tri-County EMC Mt Olive POD 115 Tap Line |
| Point of interconnection | Tri-County EMC Mt Olive POD 115 Tap Line |
| County | Duplin |
| State | NC |
| Voltage | Not reported |
| Capacity | 80 MW |
| Resource (as published) | Other |
| Resource category | Other (normalized for filtering) |
| Proposed online date | 2029-02-28 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Duplin, NC: 12 requests in the Duke Energy queue, 4 active totaling 304.8 MW.
Tracked changes
Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Duke Energy Progress |
|---|---|
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | In Progress (unknown study) |
| Study phase (as the queue printed it) | Provisional Study in Progress |
| Queue date | 2025-08-19 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.