Substation Scout

Duke Energy request PP00042

Duke Energy queue ID PP00042

Queue request PP00042 was listed in the Duke Energy interconnection queue at the end of 2025 as a 80 MW project in Granville County, NC, according to Berkeley Lab’s queue data file. The filing names Henderson - Person 230 as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 15, 2027.

Queue IDPP00042
Project nameNot reported
Status (as published)Active
SubstationHenderson - Person 230
Point of interconnectionHenderson - Person 230
CountyGranville
StateNC
VoltageNot reported
Capacity80 MW
Resource (as published)Other
Resource categoryOther (normalized for filtering)
Proposed online date2027-12-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Granville, NC: 6 requests in the Duke Energy queue, 3 active totaling 234.9 MW.

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Progress
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Pending
Study phase (as the queue printed it)Draft Provisional Interconnection Agreement
Queue date2025-06-30

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.