Granville, NC interconnection queue

3 active projects totaling 234.9 MW in the Duke Energy queue, plus 3 with terminal status (shown grayed).

3active projects
234.9active MW
6total filed
Queue IDProjectkVMWResourceStatus
915751 Not reported 230 80 Solar Active
917343 Not reported 230 80 Solar Withdrawn
PP00042 Not reported n/r 80 Other Active
569038 Not reported 230 75 Solar Withdrawn
977832 Not reported 115 74.9 Solar Active
962966 Not reported 115 55 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Duke Energy before relying on these figures.