Duke Energy request FC100008
Duke Energy queue ID FC100008
Queue request FC100008 was listed in the Duke Energy interconnection queue at the end of 2025 as a 100 MW battery project in Highlands County, FL, according to Berkeley Lab’s queue data file. The filing names Avon Park Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 31, 2029.
| Queue ID | FC100008 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Avon Park Substation |
| Point of interconnection | Avon Park Substation 69 kV |
| County | Highlands |
| State | FL |
| Voltage | 69 kV |
| Capacity | 100 MW |
| Resource (as published) | Battery |
| Resource category | Battery (normalized for filtering) |
| Proposed online date | 2029-10-31 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Highlands, FL: 13 requests in the Duke Energy queue, 4 active totaling 294.8 MW.
Tracked changes
Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Duke Energy Florida |
|---|---|
| Developer | Duke Energy Florida, LLC |
| Cluster | Cluster: 2024 Annual DEF FERC Cluster; Cluster Sub Group: South |
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Pending |
| Study phase (as the queue printed it) | Interconnection Agreement - Pending |
| Queue date | 2024-12-05 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.