Substation Scout

Duke Energy request 977788

Duke Energy queue ID 977788

Queue request 977788 was listed in the Duke Energy interconnection queue at the end of 2025 as a 22 MW project in Columbus County, NC, according to Berkeley Lab’s queue data file. The filing names Riegelwood International Paperboard Station as its point of interconnection. Its status as of December 31, 2025 was “Active”.

Queue ID977788
Project nameNot reported
Status (as published)Active
SubstationRiegelwood International Paperboard Station
Point of interconnectionRiegelwood International Paperboard 115KV Station
CountyColumbus
StateNC
Voltage115 kV
Capacity22 MW
Resource (as published)Other
Resource categoryOther (normalized for filtering)
Proposed online dateNot reported
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Columbus, NC: 9 requests in the Duke Energy queue, 2 active totaling 102 MW.

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Progress
Cluster2025 DISIS
Interconnection serviceOther
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Phase 1 Cluster Study - Study Complete
Queue date2025-06-26

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.