Queue request 977302 was listed in the Duke Energy interconnection queue at the end of 2025 as a 99 MW battery project in York County, SC, according to Berkeley Lab’s queue data file. The filing names Huckleberry Wh as its point of interconnection. Its status as of December 31, 2025 was “Active”.

Queue ID977302
Project nameNot reported
Status (as published)Active
SubstationHuckleberry Wh
Point of interconnectionHuckleberry Wh 100 kV
CountyYork
StateSC
Voltage100 kV
Capacity99 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online dateNot reported
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

York, SC: 4 requests in the Duke Energy queue, 2 active totaling 139 MW.

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Carolinas
Cluster2025 DISIS
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Phase 1 Cluster Study - Study Complete
Queue date2025-06-18

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first