Duke Energy request 957709
Duke Energy queue ID 957709
Queue request 957709 was listed in the Duke Energy interconnection queue at the end of 2025 as a 8 MW gas project in New Hanover County, NC, according to Berkeley Lab’s queue data file. The filing names Sutton Plant Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”.
| Queue ID | 957709 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Sutton Plant Substation |
| Point of interconnection | Sutton Plant Substation 115kV |
| County | New Hanover |
| State | NC |
| Voltage | 115 kV |
| Capacity | 8 MW |
| Resource (as published) | Gas |
| Resource category | Gas (normalized for filtering) |
| Proposed online date | Not reported |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Sutton Plant Substation substation: 4 requests in the Duke Energy queue, 4 active totaling 41 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 957712 | Not reported | 17 | Gas | Active |
| 957670 | Not reported | 8 | Gas | Active |
| 957687 | Not reported | 8 | Gas | Active |
New Hanover, NC: 8 requests in the Duke Energy queue, 8 active totaling 82 MW.
Tracked changes
Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Duke Energy Progress |
|---|---|
| Developer | Duke Energy Progress, LLC |
| Cluster | 2024 DISIS |
| Interconnection service | NRIS/ERIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | Cluster Study |
| Study phase (as the queue printed it) | Phase 3 Cluster Study - Study Complete |
| Queue date | 2024-06-10 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.