Substation Scout

Duke Energy request 920665

Duke Energy queue ID 920665

Queue request 920665 was listed in the Duke Energy interconnection queue at the end of 2025 as a 75 MW solar project in Union County, SC, according to Berkeley Lab’s queue data file. The filing names Midway as its point of interconnection. Its status as of December 31, 2025 was “Active”.

Queue ID920665
Project nameNot reported
Status (as published)Active
SubstationMidway
Point of interconnectionMidway
CountyUnion
StateSC
VoltageNot reported
Capacity75 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online dateNot reported
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Union, SC: 8 requests in the Duke Energy queue, 1 active totaling 75 MW.

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Carolinas
Cluster2023 Solar + Procurement
Interconnection serviceOther
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Engineering Design - In Progress
Queue date2023-09-28

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.