Substation Scout

Duke Energy request 919551

Duke Energy queue ID 919551

Queue request 919551 was listed in the Duke Energy interconnection queue at the end of 2025 as a 40 MW solar project in Lincoln County, NC, according to Berkeley Lab’s queue data file. The filing names Mull as its point of interconnection. Its status as of December 31, 2025 was “Active”.

Queue ID919551
Project nameNot reported
Status (as published)Active
SubstationMull
Point of interconnectionMull
CountyLincoln
StateNC
VoltageNot reported
Capacity40 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online dateNot reported
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Lincoln, NC: 1 request in the Duke Energy queue, 1 active totaling 40 MW.

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Carolinas
Cluster2023 Solar + Procurement
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Engineering Design - Pending
Queue date2023-09-28

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.