Queue request 566478 was listed in the Duke Energy interconnection queue at the end of 2025 as a 74.9 MW solar project in Darlington County, SC, according to Berkeley Lab’s queue data file. The filing names ROBINSON PLANT - FLORENCE as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 1, 2026.

Queue ID566478
Project nameNot reported
Status (as published)Active
SubstationROBINSON PLANT - FLORENCE
Point of interconnectionROBINSON PLANT - FLORENCE 230KV
CountyDarlington
StateSC
Voltage230 kV
Capacity74.9 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2026-12-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

ROBINSON PLANT - FLORENCE substation: 5 requests in the Duke Energy queue, 4 active totaling 294.8 MW.

Queue IDProjectMWResourceStatus
570382Not reported75SolarActive
566518Not reported74.9SolarActive
920651Not reported70SolarActive
956840Not reported50SolarWithdrawn

Darlington, SC: 40 requests in the Duke Energy queue, 21 active totaling 1,211.4 MW.

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Progress
Cluster2022 DISIS
Interconnection serviceOther
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Engineering Design - In Progress
Queue date2022-06-29

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first