Duke Energy request 4891
Duke Energy queue ID 4891
Queue request 4891 was listed in the Duke Energy interconnection queue at the end of 2025 as a 12.8 MW solar project in Onslow County, NC, according to Berkeley Lab’s queue data file. The filing names Camp Lejeune as its point of interconnection. Its status as of December 31, 2025 was “Operational”.
| Queue ID | 4891 |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | Camp Lejeune |
| Point of interconnection | Camp Lejeune |
| County | Onslow |
| State | NC |
| Voltage | Not reported |
| Capacity | 12.8 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | Not reported |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Onslow, NC: 13 requests in the Duke Energy queue, 6 active totaling 819.8 MW.
Tracked changes
Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Duke Energy Progress |
|---|---|
| Developer | Duke Energy Progress, LLC |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | Commercial Operation - Commercial Operation Date Declared |
| Queue date | 2014-10-09 |
| Operational date | 2015-11-26 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.