Duke Energy request 327
Duke Energy queue ID 327
Queue request 327 was listed in the Duke Energy interconnection queue at the end of 2025 as a 100 MW battery project in Citrus County, FL, according to Berkeley Lab’s queue data file. The filing names Powerline Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of March 1, 2027.
| Queue ID | 327 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Powerline Substation |
| Point of interconnection | Powerline Substation |
| County | Citrus |
| State | FL |
| Voltage | Not reported |
| Capacity | 100 MW |
| Resource (as published) | Battery |
| Resource category | Battery (normalized for filtering) |
| Proposed online date | 2027-03-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Citrus, FL: 22 requests in the Duke Energy queue, 9 active totaling 2,293.9 MW.
Tracked changes
Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | Duke Energy Florida |
|---|---|
| Developer | Duke Energy Florida, LLC |
| Interconnection service | ERIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | Construction |
| Queue date | 2023-05-05 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.