Duke Energy request 325

Duke Energy queue ID 325

Queue request 325 was listed in the Duke Energy interconnection queue at the end of 2025 as a 74.9 MW solar project in Osceola County, FL, according to Berkeley Lab’s queue data file. The filing names Whippoorwill Switching Station as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2026.

Queue ID325
Project nameNot reported
Status (as published)Active
SubstationWhippoorwill Switching Station
Point of interconnectionWhippoorwill Switching Station
CountyOsceola
StateFL
VoltageNot reported
Capacity74.9 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2026-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Whippoorwill Switching Station substation: 6 requests in the Duke Energy queue, 2 active totaling 149.8 MW.

Queue IDProjectMWResourceStatus
326Not reported74.9SolarActive
301Not reported74.5SolarWithdrawn
302Not reported74.5SolarWithdrawn
279Not reported74.3SolarWithdrawn
280Not reported74.3SolarWithdrawn

Osceola, FL: 23 requests in the Duke Energy queue, 7 active totaling 1,726.8 MW.

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Florida
DeveloperDuke Energy Florida, LLC
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Queue date2023-05-03

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first