Queue request 292 was listed in the Duke Energy interconnection queue at the end of 2025 as a 225 MW battery project in Pinellas County, FL, according to Berkeley Lab’s queue data file. The filing names Bartow Plant Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2025.

Queue ID292
Project nameNot reported
Status (as published)Active
SubstationBartow Plant Substation
Point of interconnectionBartow Plant Substation
CountyPinellas
StateFL
VoltageNot reported
Capacity225 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2025-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Bartow Plant Substation substation: 2 requests in the Duke Energy queue, 2 active totaling 397 MW.

Queue IDProjectMWResourceStatus
328Not reported172GasActive

Pinellas, FL: 14 requests in the Duke Energy queue, 7 active totaling 1,707 MW.

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Florida
DeveloperDuke Energy Florida, LLC
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Queue date2021-04-07

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first