Duke Energy request 149

Duke Energy queue ID 149

Queue request 149 was listed in the Duke Energy interconnection queue at the end of 2025 as a 45 MW solar project in Highlands County, FL, according to Berkeley Lab’s queue data file. The filing names Lake Placid Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of December 9, 2019.

Queue ID149
Project nameNot reported
Status (as published)Operational
SubstationLake Placid Substation
Point of interconnectionLake Placid Substation
CountyHighlands
StateFL
VoltageNot reported
Capacity45 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2019-12-09
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Lake Placid Substation substation: 2 requests in the Duke Energy queue, 1 active totaling 45 MW.

Queue IDProjectMWResourceStatus
138CNot reported74.9SolarWithdrawn

Highlands, FL: 13 requests in the Duke Energy queue, 4 active totaling 294.8 MW.

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Florida
DeveloperDuke Energy Florida, LLC
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Queue date2016-06-07
Operational date2019-11-22

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.