Substation Scout

Duke Energy request 148

Duke Energy queue ID 148

Queue request 148 was listed in the Duke Energy interconnection queue at the end of 2025 as a 74.9 MW solar project in Columbia County, FL, according to Berkeley Lab’s queue data file. The filing names Ft White - High Springs as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of March 17, 2020.

Queue ID148
Project nameNot reported
Status (as published)Operational
SubstationFt White - High Springs
Point of interconnectionFt White - High Springs
CountyColumbia
StateFL
VoltageNot reported
Capacity74.9 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2020-03-17
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Columbia, FL: 7 requests in the Duke Energy queue, 4 active totaling 298.8 MW.

Tracked changes

Not tracked. Duke Energy rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDuke Energy Florida
DeveloperDuke Energy Florida, LLC
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Queue date2016-05-27
Operational date2020-02-24

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first