Substation Scout

Liberty, FL interconnection queue

2 active projects totaling 149.8 MW in the Duke Energy queue, plus 2 with terminal status (shown grayed).

2active projects
149.8active MW
4total filed
Queue IDProjectkVMWResourceStatus
303 Not reported n/r 74.9 Solar Withdrawn
FC100018 Not reported 115 74.9 Solar Active
FC100383 Not reported n/r 74.9 Solar Active
98 Not reported n/r 14 Other Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Duke Energy before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first