Bladen, NC interconnection queue
2 active projects totaling 103 MW in the Duke Energy queue, plus 12 with terminal status (shown grayed).
2active projects
103active MW
14total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 66832 | Not reported | 230 | 450 | Solar | Withdrawn |
| 169716 | Not reported | 230 | 80 | Solar | Withdrawn |
| 32986 | Not reported | 230 | 80 | Solar | Withdrawn |
| 564034 | Not reported | 230 | 80 | Solar | Withdrawn |
| 564510 | Not reported | 230 | 80 | Solar | Active |
| 566240 | Not reported | 230 | 80 | Solar | Withdrawn |
| 890857 | Not reported | 230 | 80 | Solar | Withdrawn |
| 920641 | Not reported | n/r | 80 | Solar | Withdrawn |
| 977268 | Not reported | n/r | 80 | Solar | Withdrawn |
| 961752 | Not reported | 230 | 79.9 | Solar | Withdrawn |
| 17508 | Not reported | 230 | 60 | Solar | Withdrawn |
| 915755 | Not reported | n/r | 50 | Solar | Withdrawn |
| 4904 | Not reported | 115 | 23 | Solar | Operational |
| 899257 | Not reported | n/r | 1 | Solar | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with Duke Energy before relying on these figures.
Site Scanner