NextEra Energy Resources
BPA queue ID G88 Terminal status
| Queue ID | G88 |
|---|---|
| Project name | NextEra Energy Resources |
| Status (as published) | WITHDRAWN |
| Substation | Sacajawea Substation |
| Point of interconnection | Sacajawea Substation |
| County | Walla Walla |
| State | WA |
| Voltage | Not reported |
| Capacity | 150 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2002-09-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | NextEra Energy Resources, LLC |
|---|---|
| Connection Type | GI |
| Interconnection Type | Energy |
| Poi | Sacajawea Substation |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 150 |
| Max Summer Mw | 150 |
| Max Winter Mw | 150 |
| Reason Not Completed | . |
| Comments | Withdrawn by Customer |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.