Windy Ridge Wind Farm
BPA queue ID G85 Terminal status
| Queue ID | G85 |
|---|---|
| Project name | Windy Ridge Wind Farm |
| Status (as published) | WITHDRAWN |
| Substation | BPA's Lower Monumental Substation |
| Point of interconnection | BPA's Lower Monumental Substation |
| County | Garfield |
| State | WA |
| Voltage | Not reported |
| Capacity | 150 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2004-01-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Winds Over Washington Energy Group |
|---|---|
| Connection Type | GI |
| Interconnection Type | Energy |
| Poi | BPA's Lower Monumental Substation |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 150 |
| Max Summer Mw | 150 |
| Max Winter Mw | 150 |
| Reason Not Completed | . |
| Comments | Withdrawn by Customer |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.