BPA queue ID G79 Terminal status
| Queue ID | G79 |
|---|---|
| Project name | Horizon Wind Energy-WRidge |
| Status (as published) | WITHDRAWN |
| Substation | North Lewiston-Walla Walla line near Clarkston WA |
| Point of interconnection | 115 kV North Lewiston-Walla Walla line near Clarkston WA |
| County | Asotin |
| State | WA |
| Voltage | 115 kV |
| Capacity | 200 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2003-06-15 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Wind Ridge Power Partners, LLC |
|---|---|
| Connection Type | GI |
| Interconnection Type | Energy |
| Poi | 115 kV North Lewiston-Walla Walla line near Clarkston WA |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 200 |
| Max Summer Mw | 200 |
| Max Winter Mw | 200 |
| Reason Not Completed | . |
| Comments | Withdrawn by Customer |