300MW Lower Monumental-Starbuck
BPA queue ID G77 Terminal status
| Queue ID | G77 |
|---|---|
| Project name | 300MW Lower Monumental-Starbuck |
| Status (as published) | WITHDRAWN |
| Substation | Lower Monumental-Starbuck line. |
| Point of interconnection | Lower Monumental-Starbuck 500 kV line. |
| County | Columbia |
| State | WA |
| Voltage | 500 kV |
| Capacity | 300 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2004-06-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | RES North America |
|---|---|
| Connection Type | GI |
| Interconnection Type | Energy |
| Poi | Lower Monumental-Starbuck 500 kV line. |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 300 |
| Max Summer Mw | 300 |
| Max Winter Mw | 300 |
| Reason Not Completed | . |
| Comments | Withdrawn by Customer |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.