Cielo Wind Power

BPA queue ID G74 Terminal status

Queue IDG74
Project nameCielo Wind Power
Status (as published)WITHDRAWN
SubstationBig Eddy line South of Goldendale.
Point of interconnectionBig Eddy 230 kV line South of Goldendale.
CountyKlickitat
StateWA
Voltage230 kV
Capacity80 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2003-08-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorCielo Wind Power
Connection TypeGI
Interconnection TypeEnergy
PoiBig Eddy 230 kV line South of Goldendale.
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total80
Max Summer Mw80
Max Winter Mw80
Reason Not Completed.
CommentsWithdrawn by Customer