BPA queue ID G69 Terminal status

Queue IDG69
Project nameNational Energy and Gas Tx
Status (as published)WITHDRAWN
SubstationCoyote Springs loop on the McNary/Slatt line
Point of interconnectionCoyote Springs loop on the McNary/Slatt 500 kV line
CountyMorrow
StateOR
Voltage500 kV
Capacity620 MW
Resource (as published)Natural Gas/Gas Turbine
Resource categoryGas (normalised for filtering)
Target commercial operation2005-02-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorNational Energy & Gas Transmission, Inc.
Connection TypeGI
Interconnection TypeEnergy
PoiCoyote Springs loop on the McNary/Slatt 500 kV line
Generator TypeGas Turbine
Fuel SourceNatural Gas
Nameplate Mw Total620
Max Summer Mw620
Max Winter Mw620
Reason Not Completed.
CommentsWithdrawn by Customer