Substation Scout

100MW Harvalum

BPA queue ID G66 Terminal status

Queue IDG66
Project name100MW Harvalum
Status (as published)WITHDRAWN
SubstationHarvalum Substation
Point of interconnectionHarvalum Substation
CountyKlickitat
StateWA
VoltageNot reported
Capacity100 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2003-09-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorABB Equity Ventures Inc
Connection TypeGI
Interconnection TypeEnergy
PoiHarvalum Substation
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total100
Max Summer Mw100
Max Winter Mw100
Reason Not Completed.
CommentsWithdrawn by Customer