US Elect Power Corp
BPA queue ID G64 Terminal status
| Queue ID | G64 |
|---|---|
| Project name | US Elect Power Corp |
| Status (as published) | WITHDRAWN |
| Substation | Interconnection at Customer Substation |
| Point of interconnection | Interconnection at 230 kV Customer Substation |
| County | Whatcom |
| State | WA |
| Voltage | 230 kV |
| Capacity | 349 MW |
| Resource (as published) | Natural Gas/Gas Turbine |
| Resource category | Gas (normalised for filtering) |
| Target commercial operation | 2004-03-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | US Electric Power Corporation |
|---|---|
| Connection Type | GI |
| Interconnection Type | Energy |
| Poi | Interconnection at 230 kV Customer Substation |
| Generator Type | Gas Turbine |
| Fuel Source | Natural Gas |
| Nameplate Mw Total | 349 |
| Max Summer Mw | 349 |
| Max Winter Mw | 349 |
| Reason Not Completed | . |
| Comments | Withdrawn by Customer |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.