Substation Scout

1300MW Sickler-Schultz

BPA queue ID G60 Terminal status

Queue IDG60
Project name1300MW Sickler-Schultz
Status (as published)WITHDRAWN
SubstationSickler-Schultz
Point of interconnectionSickler-Schultz 500 kV
CountyBenton
StateWA
Voltage500 kV
Capacity1,300 MW
Resource (as published)Natural Gas/Gas Turbine
Resource categoryGas (normalised for filtering)
Target commercial operation2005-06-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorCalpine Energy Services, L.P.
Connection TypeGI
Interconnection TypeEnergy
PoiSickler-Schultz 500 kV
Generator TypeGas Turbine
Fuel SourceNatural Gas
Nameplate Mw Total1300
Max Summer Mw1300
Max Winter Mw1300
Reason Not Completed.
CommentsWithdrawn by Customer

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.