700MW Sickler-Schultz

BPA queue ID G59 Terminal status

Queue IDG59
Project name700MW Sickler-Schultz
Status (as published)WITHDRAWN
SubstationSickler-Schultz
Point of interconnectionSickler-Schultz 500 kV
CountyBenton
StateWA
Voltage500 kV
Capacity700 MW
Resource (as published)Natural Gas/Gas Turbine
Resource categoryGas (normalised for filtering)
Target commercial operation2005-06-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorCalpine Energy Services, L.P.
Connection TypeGI
Interconnection TypeEnergy
PoiSickler-Schultz 500 kV
Generator TypeGas Turbine
Fuel SourceNatural Gas
Nameplate Mw Total700
Max Summer Mw700
Max Winter Mw700
Reason Not Completed.
CommentsWithdrawn by Customer