Pacific Winds Inc
BPA queue ID G50 Terminal status
| Queue ID | G50 |
|---|---|
| Project name | Pacific Winds Inc |
| Status (as published) | WITHDRAWN |
| Substation | 230/kV McNary - Horse Heaven/ McNary - Ross line |
| Point of interconnection | 230/kV McNary - Horse Heaven/ 345 kV McNary - Ross line |
| County | Klickitat |
| State | WA |
| Voltage | 345 kV |
| Capacity | 249 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2003-03-31 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Pacific Winds, Inc. |
|---|---|
| Connection Type | GI |
| Interconnection Type | Energy |
| Poi | 230/kV McNary - Horse Heaven/ 345 kV McNary - Ross line |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 249 |
| Max Summer Mw | 249 |
| Max Winter Mw | 249 |
| Reason Not Completed | . |
| Comments | Withdrawn by Customer |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.