Substation Scout

Not reported

BPA queue ID G48 Terminal status

Queue IDG48
Project nameNot reported
Status (as published)WITHDRAWN
SubstationBig Eddy-Midway/ Hanford-John Day line
Point of interconnection230 kV Big Eddy-Midway/ 500 kV Hanford-John Day line
CountyBenton
StateWA
Voltage230 kV
Capacity150 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2002-11-15
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorWashington Winds, Inc.
Connection TypeGI
Interconnection TypeEnergy
Poi230 kV Big Eddy-Midway/ 500 kV Hanford-John Day line
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total150
Max Summer Mw150
Max Winter Mw150
Reason Not Completed.
CommentsWithdrawn on January 28, 2004

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.