50MW Alcoa

BPA queue ID G42 Terminal status

Queue IDG42
Project name50MW Alcoa
Status (as published)WITHDRAWN
SubstationAlcoa Substation in the vicinity of Vancouver, WA
Point of interconnectionAlcoa Substation 230 kV in the vicinity of Vancouver, WA
CountyClark
StateWA
Voltage230 kV
Capacity50 MW
Resource (as published)Natural Gas/Gas Turbine
Resource categoryGas (normalised for filtering)
Target commercial operation2001-10-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorCalpine Energy Services, L.P.
Connection TypeGI
Interconnection TypeEnergy
PoiAlcoa Substation 230 kV in the vicinity of Vancouver, WA
Generator TypeGas Turbine
Fuel SourceNatural Gas
Nameplate Mw Total50
Max Summer Mw50
Max Winter Mw50
Reason Not Completed.
CommentsWithdrawn by Customer