Benton PUD
BPA queue ID G27 Terminal status
| Queue ID | G27 |
|---|---|
| Project name | Benton PUD |
| Status (as published) | WITHDRAWN |
| Substation | Unocal Finley Substation |
| Point of interconnection | Unocal Finley Substation |
| County | Benton |
| State | WA |
| Voltage | Not reported |
| Capacity | 25 MW |
| Resource (as published) | Natural Gas/Gas Turbine |
| Resource category | Gas (normalised for filtering) |
| Target commercial operation | 2001-08-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Public Utility District No. 1 of Benton County |
|---|---|
| Connection Type | GI |
| Interconnection Type | Energy |
| Poi | Unocal Finley Substation |
| Generator Type | Gas Turbine |
| Fuel Source | Natural Gas |
| Nameplate Mw Total | 25 |
| Max Summer Mw | 25 |
| Max Winter Mw | 25 |
| Reason Not Completed | . |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.