500MW Taft-Bell
BPA queue ID G16 Terminal status
| Queue ID | G16 |
|---|---|
| Project name | 500MW Taft-Bell |
| Status (as published) | WITHDRAWN |
| Substation | BPA's Taft-Bell line in the vicinity of Kootenaid County, ID |
| Point of interconnection | BPA's Taft-Bell 500 kV line in the vicinity of Kootenaid County, ID |
| County | Kootenai |
| State | ID |
| Voltage | 500 kV |
| Capacity | 500 MW |
| Resource (as published) | Natural Gas/Gas Turbine |
| Resource category | Gas (normalised for filtering) |
| Target commercial operation | 2004-12-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Cogentrix Energy, Inc. |
|---|---|
| Connection Type | GI |
| Interconnection Type | Energy |
| Poi | BPA's Taft-Bell 500 kV line in the vicinity of Kootenaid County, ID |
| Generator Type | Gas Turbine |
| Fuel Source | Natural Gas |
| Nameplate Mw Total | 500 |
| Max Summer Mw | 500 |
| Max Winter Mw | 500 |
| Reason Not Completed | . |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.