LifeLine Renewable Energy
BPA queue ID G119 Terminal status
| Queue ID | G119 |
|---|---|
| Project name | LifeLine Renewable Energy |
| Status (as published) | WITHDRAWN |
| Substation | BPA's McNary - Santiam Line |
| Point of interconnection | BPA's McNary - Santiam 230kV Line |
| County | Morrow |
| State | OR |
| Voltage | 230 kV |
| Capacity | 200 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2004-10-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | Lifeline Renewable Energy, Inc. |
|---|---|
| Connection Type | GI |
| Interconnection Type | ERIS |
| Poi | BPA's McNary - Santiam 230kV Line |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 200 |
| Max Summer Mw | 200 |
| Max Winter Mw | 200 |
| Reason Not Completed | . |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.