Substation Scout

Oregon Wind

BPA queue ID G116 Terminal status

Queue IDG116
Project nameOregon Wind
Status (as published)WITHDRAWN
SubstationHood River-The Dalles Line.
Point of interconnectionHood River-The Dalles 115 KV Line.
CountyWasco
StateOR
Voltage115 kV
Capacity50 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2008-06-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorOregon Wind, LLC
Connection TypeGI
Interconnection TypeERIS
PoiHood River-The Dalles 115 KV Line.
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total50
Max Summer Mw50
Max Winter Mw50
Reason Not Completed.
CommentsWithdrawn by Customer on January 8, 2009.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.