Substation Scout

Iberdrola Renewables Inc

BPA queue ID G112 Terminal status

Queue IDG112
Project nameIberdrola Renewables Inc
Status (as published)WITHDRAWN
SubstationOn Hanford-JohnDay Line, ~8 miles SW of Bickleton
Point of interconnectionOn Hanford-JohnDay 500 kV Line, ~8 miles SW of Bickleton
CountyKlickitat
StateOR
Voltage500 kV
Capacity200 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2004-03-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorAvangrid Power, LLC
Connection TypeGI
Interconnection TypeEnergy
PoiOn Hanford-JohnDay 500 kV Line, ~8 miles SW of Bickleton
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total200
Max Summer Mw200
Max Winter Mw200
Reason Not Completed.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.