Substation Scout

Not reported

BPA queue ID G1070 Terminal status

Queue IDG1070
Project nameNot reported
Status (as published)WITHDRAWN
SubstationTucannon River: Puget Sound Energ Feeder 1
Point of interconnectionTucannon River: Puget Sound Energ 115kV Feeder 1
CountyColumbia
StateWA
Voltage115 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2027-08-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiTucannon River: Puget Sound Energ 115kV Feeder 1
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total219.5
Max Summer Mw0
Max Winter Mw0
Reason Not Completed.
CommentsCombined output not to exceed 157 MW

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.