Substation Scout

Ib

BPA queue ID G107 Terminal status

Queue IDG107
Project nameIb
Status (as published)WITHDRAWN
SubstationNear Slatt Substation
Point of interconnectionNear Slatt 500kV Substation
CountyGilliam
StateOR
Voltage500 kV
Capacity200 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2004-01-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorAvangrid Power, LLC
Connection TypeGI
Interconnection TypeEnergy
PoiNear Slatt 500kV Substation
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total200
Max Summer Mw200
Max Winter Mw200
Reason Not Completed.
CommentsWithdrawn per 12/16/2003 letter from Customer.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.