BPA queue ID G1064 Terminal status
| Queue ID | G1064 |
|---|---|
| Project name | Not reported |
| Status (as published) | WITHDRAWN |
| Substation | UEC Westland to McNary line that terminates in the Bay 16 terminal of the McNary Substation. |
| Point of interconnection | UEC Westland to McNary 230 kV line that terminates in the 230 kV Bay 16 terminal of the McNary Substation. |
| County | Umatilla |
| State | OR |
| Voltage | 230 kV |
| Capacity | 15 MW |
| Resource (as published) | Battery/Energy Storage |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2026-01-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Connection Type | GI |
|---|---|
| Interconnection Type | ERIS |
| Poi | UEC Westland to McNary 230 kV line that terminates in the 230 kV Bay 16 terminal of the McNary Substation. |
| Generator Type | Energy Storage |
| Fuel Source | Battery |
| Nameplate Mw Total | 15 |
| Max Summer Mw | 15 |
| Max Winter Mw | 15 |
| Reason Not Completed | . |