Desert Claim
BPA queue ID G105 Terminal status
| Queue ID | G105 |
|---|---|
| Project name | Desert Claim |
| Status (as published) | WITHDRAWN |
| Substation | Covington-Columbia transmission line |
| Point of interconnection | Covington-Columbia 230kV transmission line |
| County | Kittitas |
| State | WA |
| Voltage | 230 kV |
| Capacity | 159 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2009-10-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Requestor | enXco Northwest |
|---|---|
| Connection Type | GI |
| Interconnection Type | ERIS |
| Poi | Covington-Columbia 230kV transmission line |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 159 |
| Max Summer Mw | 159 |
| Max Winter Mw | 159 |
| Reason Not Completed | Awaiting Customer Permits To Complete NEPA Review |
| Comments | New plan-of-serivce per customer request, site permits approved; FAS issued 2/4/13 |