Not reported
BPA queue ID G1043 Terminal status
| Queue ID | G1043 |
|---|---|
| Project name | Not reported |
| Status (as published) | WITHDRAWN |
| Substation | On the Rocky Ford-Coulee transmission line approximately 21 miles northeast of Rocky Ford substation. |
| Point of interconnection | On the Rocky Ford-Coulee 230kV transmission line approximately 21 miles northeast of Rocky Ford substation. |
| County | Grant |
| State | WA |
| Voltage | 230 kV |
| Capacity | 150 MW |
| Resource (as published) | Battery/Energy Storage |
| Resource category | Battery (normalised for filtering) |
| Target commercial operation | 2026-12-31 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Connection Type | GI |
|---|---|
| Interconnection Type | NRIS & ERIS |
| Poi | On the Rocky Ford-Coulee 230kV transmission line approximately 21 miles northeast of Rocky Ford substation. |
| Generator Type | Energy Storage |
| Fuel Source | Battery |
| Nameplate Mw Total | 300 |
| Max Summer Mw | 150 |
| Max Winter Mw | 150 |
| Cluster | Transition Cluster |
| Reason Not Completed | . |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.