Substation Scout

Not reported

BPA queue ID G1023 Terminal status

Queue IDG1023
Project nameNot reported
Status (as published)WITHDRAWN
SubstationPonderosa Substation
Point of interconnectionPonderosa Substation
CountyLake
StateOR
VoltageNot reported
Capacity500 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2030-06-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiPonderosa Substation
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total1023.6
Max Summer Mw500
Max Winter Mw500
ClusterTransition Cluster
Reason Not Completed.