Not reported

BPA queue ID G1021 Terminal status

Queue IDG1021
Project nameNot reported
Status (as published)WITHDRAWN
SubstationLexington Substation
Point of interconnectionLexington Substation
CountyCowlitz
StateWA
VoltageNot reported
Capacity500 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2028-12-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiLexington Substation
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total530.4
Max Summer Mw500
Max Winter Mw500
ClusterTransition Cluster
Reason Not Completed.